If it takes 100 minutes to complete a circuit,demand at the next work center is 5 parts per minute,and a container will hold 20 parts,how many containers are required?


A) 25
B) 5
C) 40
D) 20

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

If a work center has no empty containers,the workers at the work center will do which of the following?


A) Continue to produce as much inventory as they can
B) Produce enough inventory to meet the following day's demand
C) Produce enough inventory to satisfy the master production schedule
D) Stop production

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

External setup time refers to:


A) The time it takes workers to set up a machine during scheduled maintenance
B) The time to complete setup activities that do not require that the machine be stopped
C) The time it takes equipment vendors to set up the machine
D) None of the above

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

Which of the following is not required for a lean system?


A) Flexible workforce
B) A Type II MRP system
C) A stable master schedule
D) Kanban pull system

E) B) and D)
F) A) and B)

Correct Answer

verifed

verified

With lean thinking,a company's operations layout should evolve to a cellular manufacturing layout.

A) True
B) False

Correct Answer

verifed

verified

With regards to suppliers,lean systems typically require:


A) Delivery of large lots at frequent intervals
B) Buyer inspection of goods and materials
C) Multiple sources from which to purchase
D) Long-term relationships and commitments
E) The lowest price possible

F) B) and C)
G) A) and C)

Correct Answer

verifed

verified

A kanban card is used to signal that:


A) The next work center is stopped
B) A materials handler has run out of parts
C) A machine has broken down
D) Parts are needed by the subsequent work center
E) A machine is ready for preventive maintenance

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

Value stream maps are similar to flowcharts and are used for identifying the waste and non-value-added steps in the current process.

A) True
B) False

Correct Answer

verifed

verified

The ideal lot size for a lean system is:


A) Infinite
B) One
C) The capacity of the machine
D) Variable according to the production requirements
E) None of the above

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

Which of the following is not an element of lean?


A) Small-lot production
B) Modularized master schedule
C) Multifunction workers
D) Kanban pull system
E) Perfect or nearly perfect quality

F) None of the above
G) A) and B)

Correct Answer

verifed

verified

According to the lean philosophy,it is required to maintain a stable master production schedule to reduce the work-in-process inventories.

A) True
B) False

Correct Answer

verifed

verified

Why is production leveled in a lean system?


A) To create a uniform workload on all work centers
B) To allow for production of safety stock
C) To signal the need for more parts
D) To increase the time for scheduled maintenance

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Reduction of setup time is accomplished by separating internal and external setups and:


A) Reducing inventory
B) Implementing a Kanban system
C) Converting internal setup time to external setup time
D) Reducing lot sizes

E) A) and C)
F) C) and D)

Correct Answer

verifed

verified