A(n)____________________ is a starting point,a measurement,or an observation that is documented so that it can be used for future comparison.

Correct Answer

verifed

verified

Duration estimates are provided as a ____ number,such as four weeks; as a range,such as three to five weeks; or as a three-point estimate.


A) continuous
B) random
C) fractional
D) discrete

E) A) and D)
F) A) and C)

Correct Answer

verifed

verified

The activity ____________________ is a tabulation of activities to be included on a project schedule.

Correct Answer

verifed

verified

Planning includes tasks related to each of the ____ project management knowledge areas.


A) four
B) five
C) nine
D) sixteen

E) C) and D)
F) B) and D)

Correct Answer

verifed

verified

____________________ is the number of workdays or work hours required to complete a task.

Correct Answer

verifed

verified

The precedence diagramming method uses only finish-to-start dependencies.

A) True
B) False

Correct Answer

verifed

verified

____________________ is a network analysis technique used to estimate project duration when there is a high degree of uncertainty about the individual activity duration estimates.

Correct Answer

verifed

verified

Program Evaluation and Review ...

View Answer

The WBS is a peripheral document in project management.

A) True
B) False

Correct Answer

verifed

verified

____________________ modeling uses project characteristics (parameters)in a mathematical model to estimate project costs.

Correct Answer

verifed

verified

After defining project activities,the next step in project time management is activity ____.


A) organization
B) sequencing
C) segmenting
D) ordering

E) C) and D)
F) A) and D)

Correct Answer

verifed

verified

Activity ____ provide schedule-related information about each activity,such as predecessors,successors,logical relationships,leads and lags,resource requirements,constraints,imposed dates,and assumptions related to the activity.


A) features
B) characteristics
C) properties
D) attributes

E) C) and D)
F) None of the above

Correct Answer

verifed

verified

The project manager should work with his or her team and ____ to determine the level of detail needed in the WBS dictionary.


A) client
B) customer
C) auditor
D) sponsor

E) B) and D)
F) A) and D)

Correct Answer

verifed

verified

It is poor practice to use more than one approach for creating a cost estimate.

A) True
B) False

Correct Answer

verifed

verified

Fast ____________________ involves doing activities in parallel that you would normally do in sequence.

Correct Answer

verifed

verified

A(n) ____ path for a project is the series of activities that determine the earliest time by which the project can be completed.


A) integral
B) incidental
C) critical
D) vital

E) None of the above
F) A) and D)

Correct Answer

verifed

verified

Explain why project management plans need to be dynamic,flexible,and receptive to change when the environment or project changes.

Correct Answer

verifed

verified

Project management plans should be dynam...

View Answer

The main disadvantage of ____ is that it can end up lengthening the project schedule,because starting some tasks too soon often increases project risk and results in rework.


A) reviewing
B) crashing
C) extending
D) fast tracking

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

The PMBOK Guide lists over ____ documents that project teams can produce as part of project planning.


A) 50
B) 75
C) 100
D) 125

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

The contents of scope statements can vary.

A) True
B) False

Correct Answer

verifed

verified

Project management ____ facilitate communication among stakeholders and provide a baseline for progress measurement and project control.


A) charters
B) plans
C) contracts
D) compacts

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified