Filters
Question type

Study Flashcards

Expected standards generally yield favorable variances.

A) True
B) False

Correct Answer

verifed

verified

Expected standards generally yield unfavorable variances.

A) True
B) False

Correct Answer

verifed

verified

When computing variances from standard costs,the difference between actual and standard price multiplied by actual quantity used yields a


A) combined price-quantity variance.
B) price variance.
C) quantity variance.
D) mix variance.

E) A) and D)
F) A) and B)

Correct Answer

verifed

verified

A conversion variance combines labor and overhead variances.

A) True
B) False

Correct Answer

verifed

verified

The formula for price/rate variance is (AP - SP)´ SQ.

A) True
B) False

Correct Answer

verifed

verified

The fixed overhead application rate is a function of a predetermined activity level.If standard hours allowed for good output equal the predetermined activity level for a given period,the volume variance will be


A) zero.
B) favorable.
C) unfavorable.
D) either favorable or unfavorable,depending on the budgeted overhead.

E) All of the above
F) None of the above

Correct Answer

verifed

verified

Reichs Company The following information is for Reichs Company's September production:  Standard:  Material 4.0 feet per unit @$3.75 per foot  Labor 3.0 hours per unit @$8.25 per hour \begin{array}{ll}\textbf { Standard: }\\\text { Material } & 4.0 \text { feet per unit } @ \$ 3.75 \text { per foot } \\\text { Labor } & 3.0 \text { hours per unit } @ \$ 8.25 \text { per hour }\end{array}  Actual:  Production 3,500 units produced during the month  Material 14,200 feet used; 14,700 feet purchased @ $3.70 per foot  Labor 10,400 direct labor hours $8.35 per hour \begin{array}{ll}\textbf { Actual: }\\\text { Production } & 3,500 \text { units produced during the month } \\\text { Material } & 14,200 \text { feet used; } 14,700 \text { feet purchased @ } \$ 3.70\text { per foot } \\\text { Labor } & 10,400 \text { direct labor hours } \$ 8.35\text { per hour }\end{array} (Round all answers to the nearest dollar.) Refer to Reichs Company.What is the material price variance (calculated at point of purchase) ?


A) $ 735 F
B) $ 735 U
C) $ 710 F
D) $ 710 U

E) B) and C)
F) C) and D)

Correct Answer

verifed

verified

Hidalgo Company has made the following information available for its production facility for the current month.Fixed overhead was estimated at 19,000 machine hours for the production cycle.Actual machine hours for the period were 18,900,which generated 3,900 units. Hidalgo Company has made the following information available for its production facility for the current month.Fixed overhead was estimated at 19,000 machine hours for the production cycle.Actual machine hours for the period were 18,900,which generated 3,900 units.    Hidalgo Company's standard costs are as follows:    Determine the following items:   Hidalgo Company's standard costs are as follows: Hidalgo Company has made the following information available for its production facility for the current month.Fixed overhead was estimated at 19,000 machine hours for the production cycle.Actual machine hours for the period were 18,900,which generated 3,900 units.    Hidalgo Company's standard costs are as follows:    Determine the following items:   Determine the following items: Hidalgo Company has made the following information available for its production facility for the current month.Fixed overhead was estimated at 19,000 machine hours for the production cycle.Actual machine hours for the period were 18,900,which generated 3,900 units.    Hidalgo Company's standard costs are as follows:    Determine the following items:

Correct Answer

verifed

verified

The following information is available from the Fitzgerald Company:  Actual OH $15,000 Fixed OH expenses, actual $7,200 Fixed OH expenses, budgeted $7,000 Actual hours 3,500 Standard hours 3,800 Variable OH rate per DLH $2.50\begin{array}{ll}\text { Actual OH } & \$ 15,000 \\\text { Fixed OH expenses, actual } & \$ 7,200 \\\text { Fixed OH expenses, budgeted } & \$ 7,000 \\\text { Actual hours } & 3,500 \\\text { Standard hours } & 3,800 \\\text { Variable OH rate per DLH } & \$ 2.50\end{array} Assuming that Fitzgerald uses a three-way analysis of overhead variances,what is the overhead spending variance?


A) $750 F
B) $750 U
C) $950 F
D) $1,500 U

E) All of the above
F) A) and D)

Correct Answer

verifed

verified

Wimberly Company Wimberly Company has the following information available for March when 4,200 units were produced (round answers to the nearest dollar) . Wimberly Company Wimberly Company has the following information available for March when 4,200 units were produced (round answers to the nearest dollar) .   Refer to Wimberly Company.Assume that the company computes the material price variance on the basis of material issued to production.What is the total material variance? A) $1,050 U B) $1,050 F C) $3,030 U D) $3,030 F Refer to Wimberly Company.Assume that the company computes the material price variance on the basis of material issued to production.What is the total material variance?


A) $1,050 U
B) $1,050 F
C) $3,030 U
D) $3,030 F

E) None of the above
F) All of the above

Correct Answer

verifed

verified

The difference between budgeted and applied fixed factory overhead is referred to as a __________________________________________________.

Correct Answer

verifed

verified

fixed over...

View Answer

Starr Company has made the following information available for its production facility for the current month.Fixed overhead was estimated at 22,000 machine hours for the production cycle.Actual machine hours for the period were 21,700,which generated 4,200 units. Starr Company has made the following information available for its production facility for the current month.Fixed overhead was estimated at 22,000 machine hours for the production cycle.Actual machine hours for the period were 21,700,which generated 4,200 units.    Starr Company's standard costs are as follows:    Determine the following items:   Starr Company's standard costs are as follows: Starr Company has made the following information available for its production facility for the current month.Fixed overhead was estimated at 22,000 machine hours for the production cycle.Actual machine hours for the period were 21,700,which generated 4,200 units.    Starr Company's standard costs are as follows:    Determine the following items:   Determine the following items: Starr Company has made the following information available for its production facility for the current month.Fixed overhead was estimated at 22,000 machine hours for the production cycle.Actual machine hours for the period were 21,700,which generated 4,200 units.    Starr Company's standard costs are as follows:    Determine the following items:

Correct Answer

verifed

verified

Fleetwood Company Fleetwood Company uses a standard cost system for its production process and applies overhead based on direct labor hours.The following information is available for May when Fleetwood produced 4,500 units:  Standard:  DLH per unit 2.50 Variable overhead per DLH $1.75 Fixed overhead per DLH $3.10 Budgeted variable overhead $21,875 Budgeted fixed overhead $38,750 Actual: Direct labor hours 10,000 Variable overhead$26,250 Fixed overhead$38,000\begin{array}{ll}\text { Standard: }\\\text { DLH per unit } & 2.50 \\\text { Variable overhead per DLH } & \$ 1.75 \\\text { Fixed overhead per DLH } & \$ 3.10 \\\text { Budgeted variable overhead } & \$ 21,875 \\\text { Budgeted fixed overhead } & \$ 38,750\\\\\text { Actual: }\\\text {Direct labor hours }&10,000\\\text { Variable overhead}&\$26,250\\\text { Fixed overhead}&\$38,000\\\end{array} Refer to Fleetwood Company.Using the one-variance approach,what is the total overhead variance?


A) $6,062.50 U
B) $3,625.00 U
C) $9,687.50 U
D) $6,562.50 U

E) All of the above
F) A) and D)

Correct Answer

verifed

verified

The material price variance (computed at point of purchase) is


A) the difference between the actual cost of material purchased and the standard cost of material purchased.
B) the difference between the actual cost of material purchased and the standard cost of material used.
C) primarily the responsibility of the production manager.
D) both a and c.

E) All of the above
F) None of the above

Correct Answer

verifed

verified

Management would generally expect unfavorable variances if standards were based on which of the following capacity measures? Ideal        Practical           Expected annual\underline{\text{Ideal}} ~~~~~~~~\underline{\text{Practical}} ~~~~~~~~~~~\underline{\text{Expected annual}}


A) yes no no
B) no no no
C) no yes yes
D) yes yes no

E) A) and B)
F) A) and D)

Correct Answer

verifed

verified

Ritchie Company Ritchie Company uses a standard cost system for its production process.Ritchie Company applies overhead based on direct labor hours.The following information is available for July: Ritchie Company Ritchie Company uses a standard cost system for its production process.Ritchie Company applies overhead based on direct labor hours.The following information is available for July:   Refer to Ritchie Company Using the two-variance approach,what is the controllable variance? A) $21,650 U B) $16,480 U C) $5,775 U D) $12,080 U Refer to Ritchie Company Using the two-variance approach,what is the controllable variance?


A) $21,650 U
B) $16,480 U
C) $5,775 U
D) $12,080 U

E) B) and D)
F) B) and C)

Correct Answer

verifed

verified

Which of the following statements regarding standard cost systems is true?


A) Favorable variances are not necessarily good variances.
B) Managers will investigate all variances from standard.
C) The production supervisor is generally responsible for material price variances.
D) Standard costs cannot be used for planning purposes since costs normally change in the future.

E) A) and D)
F) B) and D)

Correct Answer

verifed

verified

When multiple materials are used,the difference between the total quantity and the standard quantity of output when a nonstandard mix of materials is used is known as the _________________________ variance.

Correct Answer

verifed

verified

Ideal standards are an effective means of controlling variances and motivating workers.

A) True
B) False

Correct Answer

verifed

verified

When multiple labor categories are used,the monetary impact of using a higher or lower number of hours than a standard allows is referred to as a ______________________________ variance.

Correct Answer

verifed

verified

Showing 81 - 100 of 220

Related Exams

Show Answer