A project superintendent is about to begin work on a freeway resurfacing project,which is comprised of the following five activities: A project superintendent is about to begin work on a freeway resurfacing project,which is comprised of the following five activities:   What is the probability that the critical path for this project will be completed within 52 weeks? A) 0.1554 B) 0.3108 C) 0.3466 D) 0.6554 E) 0.8277 What is the probability that the critical path for this project will be completed within 52 weeks?


A) 0.1554
B) 0.3108
C) 0.3466
D) 0.6554
E) 0.8277

F) C) and E)
G) B) and C)

Correct Answer

verifed

verified

Given this information about activity B: ES = 10,EF = 15,LS = 16 and LF = 21,we can determine that the amount of slack associated with the activity is:


A) 0
B) 1
C) 5
D) 6
E) 11

F) A) and D)
G) All of the above

Correct Answer

verifed

verified

Once a project is underway,project managers are only responsible for managing the project schedule (time)and budget (costs).

A) True
B) False

Correct Answer

verifed

verified

A beta distribution can be used to describe the inherent variability of an activity's duration.

A) True
B) False

Correct Answer

verifed

verified

Which of the following would probably not involve the use of project management?


A) Planning and constructing a new city hall
B) Developing a marketing campaign for the launch of a new product
C) Designing and constructing a subway system
D) Scheduling workers and purchasing raw materials for a manufacturing plant
E) Producing and staging a music festival

F) None of the above
G) A) and D)

Correct Answer

verifed

verified

Activity C has an early start time of 8,an early finish time of 12,a latest start time of 13,and a latest finish time of 17.Its slack is:


A) 0
B) 1
C) 4
D) 5
E) 9

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

What is the estimated standard deviation (in weeks)for the critical path completion time? 11eab92b_c478_4548_99e6_5b8bd904f866

Correct Answer

verifed

verified

The Project Manager is about to begin a project comprised of the following six activities: The Project Manager is about to begin a project comprised of the following six activities:   What is the estimated standard deviation of the duration for activity E? A) 2 days B) 3 days C) 4 days D) 16 days E) 24 days What is the estimated standard deviation of the duration for activity E?


A) 2 days
B) 3 days
C) 4 days
D) 16 days
E) 24 days

F) None of the above
G) C) and D)

Correct Answer

verifed

verified

In crashing this project to 18 weeks,which activities (in order of selection)will be reduced? 11eab92b_c478_936d_99e6_fd6fdfc10bad

Correct Answer

verifed

verified

The earliest finish time for an activity is equal to the latest finish time minus the activity slack.

A) True
B) False

Correct Answer

verifed

verified

A relatively simple tool for planning and scheduling simple projects is the:


A) an activity-on-arrows network.
B) an activity-on-nodes network.
C) a Gantt chart.
D) critical path method.
E) program evaluation and review technique.

F) A) and D)
G) B) and E)

Correct Answer

verifed

verified

The standard deviation of a project duration is equal to the sum of the variances of all the activities of the project.

A) True
B) False

Correct Answer

verifed

verified

A project superintendent is about to begin work on a freeway resurfacing project,which is comprised of the following five activities: A project superintendent is about to begin work on a freeway resurfacing project,which is comprised of the following five activities:   What is the estimated slack time for Activity E? A) 0 weeks B) 3 weeks C) 9 weeks D) 11 weeks E) 12 weeks What is the estimated slack time for Activity E?


A) 0 weeks
B) 3 weeks
C) 9 weeks
D) 11 weeks
E) 12 weeks

F) B) and D)
G) A) and B)

Correct Answer

verifed

verified

A PERT/CPM activity has an optimistic duration estimate of 3 days,a most likely duration estimate of 8 days,and a pessimistic duration estimate of 10 days.The expected duration of this activity te is:


A) 7.0
B) 7.5
C) 8.0
D) 8.5
E) 10.0

F) B) and C)
G) A) and E)

Correct Answer

verifed

verified

Which of the following is not a part of project scheduling?


A) Identify resource requirements for activities
B) Estimate the duration of activities
C) Identify activities in the work breakdown structure
D) Identify sequential dependencies among activities
E) Risk management planning

F) A) and E)
G) B) and C)

Correct Answer

verifed

verified

In a precedence network the critical path is the sequence of activities which has:


A) the most activities.
B) the most nodes.
C) the most events.
D) the longest duration.
E) the greatest variance.

F) C) and E)
G) C) and D)

Correct Answer

verifed

verified

The Project Manager is about to begin a project comprised of the following six activities: The Project Manager is about to begin a project comprised of the following six activities:   What is the estimated slack time for the path A-D-F? A) 0 days B) 20 days C) 40 days D) 60 days E) 100 days What is the estimated slack time for the path A-D-F?


A) 0 days
B) 20 days
C) 40 days
D) 60 days
E) 100 days

F) A) and D)
G) None of the above

Correct Answer

verifed

verified

A project manager for Durable Construction Co.is about to build a house involving the following six activities: A project manager for Durable Construction Co.is about to build a house involving the following six activities:   What is the probability that the critical path for this project will be completed within 210 days? A) 0.5000 B) 0.8413 C) 0.9544 D) 0.9772 E) 0.9987 What is the probability that the critical path for this project will be completed within 210 days?


A) 0.5000
B) 0.8413
C) 0.9544
D) 0.9772
E) 0.9987

F) A) and B)
G) A) and C)

Correct Answer

verifed

verified

What are the estimated expected (mean)durations (in weeks)for activities A-H? 11eab92b_c478_1e33_99e6_3768d426c27c

Correct Answer

verifed

verified

A = 15; B = 20; C = ...

View Answer

What are the estimated standard deviations (in weeks)of the durations for activities A-H? 11eab92b_c478_1e34_99e6_bfa52d4f4d37

Correct Answer

verifed

verified

A = 2; B = 1.67; C =...